POST-CUTOVER OPERATIONS

Hypercare & first-cycle exit

Do not declare success at cutover. Exit hypercare only after customer, billing, payment, meter and incident evidence remains inside agreed thresholds.

88% gates passing

First 72 hours acceptance checks

MetricValueLimitStatus
critical incidents00pass
open p1 defects32fail
billing variance pct0.040.1pass
unreconciled payments ksh21805000pass
read completeness pct98.798pass
complaint rate pct1.32pass
rollback events00pass
data quality errors710pass

Hypercare exit

Stay in hypercareFailed: open_p1_defects
Exit remains an authorized operational decision, not an automatic software action.